Project Overview: EPC FPSO Topsides Modules for PTSC Lam Son FPSO for the Thang Long Dong Do Field.
Project Scope:
- EPC for full topsides modules (3,000 T).
- Flare Knock out System
- Gas Dehydration and Dew Point Control
- Product, Produced Water &Chemical Injection
- Sea Water Injection & Cooling Water
- Gas Export Compression
- Gas Recompression
- Open and Closed Drains Skid
Key Milestones:
- 1.2 million man hours without LTI.
- Delivered on Schedule
Location
Vietnam.
Contract Awarded
February 2011
Completion Date
February 2013